2020
- Roundwood NZ – Boiler relocation, including new Header & pipelines
- CHH Plywood – Hot press & Hydraulic cylinders welding repair work.
- NZ Manuka – Annual servicing & steaming tests of local and remote location boilers.
2019
- AFFCO Nationwide safety inspections of all their operational boilers.
- Whakatane Mill – No.4 power boiler project – upgraded to Unattended status.
- PanPac Napier – steam valves replacement & boiler tube repairs.
- Methanex – R441 boiler – supply & install replacement wall tubes.
- Fonterra Stirling – Winter Annual service & maintenance program.
- Fonterra Reporoa – Annual servicing of 2 boilers.
- Boiler operator training for Fonterra Stirling & Cedenco Foods.
2018
- OJIFS Tasman – Recovery boiler and Steam plant annual shut welding & fitting.
- OJIFS Kinleith – Tube bending & supply – 2″ gun port boiler tube spares.
- Nova Energy Edgecumbe – Boiler wall tube repairs.
- CHH Woodproducts – Annual shut pipework & ASME welding.
- A number of Fonterra factories nationwide – Winter Annual maintenance.
- Manildra Starches Australia – major upgrades to Boilers 2, 4 & 6.
- Natures Flame – Repairs to Kidney plate and replace tubes.
- Bega Cheese Australia – Boiler combustion upgrade.
- PanPac – Boiler & economiser tube repairs.
2017
- Pukepine , TePuke – Modify, retube & install 2nd firetube boiler.
- Manildra Starches – Planning for Boiler retube & major plant upgrades.
- Trustpower – Matahina dam turbine runner repairs in situ.
- Boiler Quarterly & Annual Surveys & servicing at our client sites during year.
- Fonterra – Annual maintenance & quarterly surveys across many of their sites.
- Purepine Mouldings – Cochran boiler retube and steam piping projects.
- OJIFS Kinleith – #3PB & RB5 Annual shut pipe, tube & general welding work.
- PanPac Napier – Steam coils, boiler tube repairs and welding services.
2016
- Fonterra Waitoa – 3x boiler grates & multi-cyclone annual maintenance.
- OJIFS Tasman – Evaps dome supply and replacement.
- Alliance Meats – Mud drum repair & blowdown pipe replacement.
- PanPac Napier – Boiler blowdown vessel relocation.
- PanPac Napier – Boiler 2 wall tube repairs.
- OJIFS Tasman – Power Boiler secondary Superheater tubes repairs.
- Manildra Starches – Boiler 5 lower economiser replacement.
- Manildra Starches – Boiler 6 Economiser & grit reticulation system.
- Iceland Drilling – Geothermal pipework modifications.
- Ballance Kapuni – Mud drum header repairs.
2015
- Fonterra Waitoa – 3x boiler grates & multi-cyclone annual maintenance.
- Manildra Starches – Boiler 5 retube, upgrade and repair works.
- CHH Tasman – Shut works.
- CHH Kinleith – Shut works.
- BR & SL Porter – Installation of 1820Kg/Hr steam boiler.
- PanPac Napier – Economiser manufacture & installation.
- Fonterra Tirau – Deaerator repair & pipework.
2014
- Fonterra Waitoa – Precipitator, 3x boiler grates & multi-cyclone annual maintenance.
- Fonterra Edendale – #3 Boiler Partial retube.
- Fonterra Stirling – 8MW Boiler retube.
- CHH Tasman & Kinleith – Shut works.
- Methanex Motonui – Front wall refractory replacement.
- Methanex Waitara Valley – Boiler sidewall tubes replacement.
- Leader Foods – install heat plant & pipework.
2013
- Ballance Kapuni – 30TPH Waste Heat boiler gas train.
- North Island Mussels – Re-route cooker steam line.
- BR&SL Porter – Boiler tube plate repair.
- Pukepine, TePuke – Reroll Boiler Tubes and Repair.
- Norske Skog, Kawerau – TA3 Exhaust and Ducting.
- CHH Tasman, Kawerau – March Shut.
- CHH Tasman, Kawerau – Repair Cracks in Superheater.
- Cedenco Foods, Gisborne – Repairs to Boiler.
- CHH Kinleith, Tokoroa – May Shut and Installation of Cascade Wheel.
2012
- Ballance Agri Nutrients Kapuni, Design/Fabrication, Supply, Installation, Commissioning to Commercial Steaming Standards of 30t/hr Waste Heat Flue Gas Boiler.
- CHH Tasman, Shut Work.
- Fonterra Waitoa, Boiler 4 Grate Overhaul.
- PanPac Forest Products, Economiser Repairs.
- Trust Power, Cavatation Preventation /Monitoring/ Repair.
- Fonterra Waitoa, Grate Shaft Bearing Replacement.
- CHH Kinleith, May and September Shuts.
- CHH Woodproducts-Whangerei, Tube Expanding.
- Fonterra Waitoa, Machine Shaft and Install Grate Seals. CHH Kinleith, Fabricate and Install Causticisng Spools.
- Manildra Starches, Australia, Replace Economiser Elements.
- Transfield Worley, Design/Fabrication, Supply, Installation, Commissioning to Commercial Steaming Standards of 7mw Lignite Coal Fired Boiler.
2011
- Kinleith – May and September Shuts.
- Kinleith – RB4 Sootblower Isolation Valves.
- Kinleith – Installation of Pipebridge.
- Tasman – Shuts, Handrails on Hot Lime Tanks.
- Kinleith – RB4 Roof and Wall Tubes.
- Westland Milk Products – Retractable Sootblower Installation.
- Fonterra Waitoa – Grate castings spares.
- Fonterra Waitoa – Re-build of Grate.
- Fonterra Hautapu – Re-tube Boiler.
- Fonterra Hautapu – No. 2, Grate Repairs.
- Open Country Dairy Co – Supply of Enchem Level 2 Boiler Operators.
- Fonterra Takaka – Repair Re-circulating Duct in Air-Heater.
- Ballance Agri Nutrients Tauranga – Superheater Fabrication and commissioning.
2010
- Fonterra Waitoa, Grate Repairs.
- North Island Mussel Processors, S/S Steam Line.
- PanPac Forest Products, Installation of Economiser.
- H.C Extractions (Australia), Installation of Heat Recovery Oil Heater.
- CHH Tasman – Repair Air Heater Elements.
- PR & S Snook & Sons – Refurbish Boiler.
- CHH Kinleith – Repairs to Cascade Wheel.
- Whakatane Hospital – Steam Compliance.
- Pan Pac Forests – Boiler Survey.
- Bega Cheese Australia– Repair leaks and refractory maintenance.
- Manildra Starches, Nowra, Australia – Generating Bank Re-tube.